[DONE] Scheduled service window 9th Jan 00:00 - 06:00 CET

Update 2018-01-09

Due to the meltdown and spectre exploits we had to replan the work durung this service window. Instead of the planned network upgrade we replaced network HW and upgraded Jelastic v2 (NEW) compute nodes instead.

--- 

This is a network upgrade in sto2 to prepare for our third datacenter sto3 in Openstack and Jelastic. This work increases the risk for network disturbance during the service window.

Time of maintenance:

Tuesday 9th January between 00:00 - 06:00 CET
(Note - This is Monday night moving into Tuesday)
Availability Zone: sto2

Systems affected:
Increased risk for network disturbance.  
No customer environments downtime expected!

Was this article helpful?
0 out of 0 found this helpful
Have more questions? Submit a request

Comments

0 comments

Article is closed for comments.